Northern California

Fairfield Civic Center Library

2020-10-27T11:35:12-07:00

Allana Buick & Bers, Inc. (ABB) was retained by the County of Solano to identify
sources of moisture infiltration and design remedial repairs for the Fairfield Civic
Center Library.
The library is a one and two story concrete framed structure consisting of cast-inplace
and pre-cast structural and wall elements. The existing roof systems consisted
of

Pointe Pacific Homeowner’s Association

2020-10-07T22:21:56-07:00

Allana Buick & Bers, Inc. was retained by the HOA to provide forensic investigation of the building envelope and provide reports regarding the siding, decks, stairs, roof and window systems.

Pointe Pacific is a 400-unit, 40-building complex, located high on the hill in Daly City. Allana Buick & Bers provided investigation and

Housing Authority of the County of Santa Clara – Deborah Drive

2020-10-07T22:23:23-07:00

Allana Buick & Bers, Inc. was selected by the Housing Authority of the County of Santa Clara (HACSC) to provide investigation, design and construction phase services to the Deborah Drive Apartment Complex located in Santa Clara California.

Deborah Drive is a four unit apartment complex consisting of one and two

Lakeside Administration Building

2020-10-07T22:27:11-07:00

Allana Buick & Bers  was hired to evaluate building leaks and the overall building envelope condition for a 12-story county administration building.

Allana Buick & Bers performed a leak detection study and reviewed conditions. We provided cost analysis and recommendations for repair. The building has several county departments as tenants, including the General

Cesar Chavez Student Center – San Francisco State University

2020-10-07T22:27:59-07:00

Allana Buick & Bers was retained by San Francisco State University (SFSU) to provide forensic investigation and remedial repair solutions for water leaks related to the exterior of a community building on a college campus.

The Cesar Chavez Student Center at SFSU was originally built in 1975. The concrete building

Bannan Hall – Santa Clara University

2020-10-07T22:28:33-07:00

Allana Buick & Bers was retained by Santa Clara University (SCU) to provide forensic investigation and construction management services for exterior cladding issues occurring at Bannan Hall on the SCU campus.

Bannan Hall was completed in 1991. The three-story, 90,000 SF steel-frame building contains SCU’s civil and mechanical engineering schools.

Pinnacle Galleria

2020-10-07T22:29:22-07:00

Allana Buick & Bers, Inc. was retained by BRE Properties (BRE), a Real Estate Investment Trust (REIT) to provide forensic investigation, construction defect litigation support and rehabilitation, roofing and building envelope consulting services.

Pinnacle Galleria has 15 buildings that are two and three-story wood frame construction with a concrete foundation.